. The Factory . New expansion - 2019 (Construction phase 4)

  • Plot before the beginning of the construction
  • Ground ready for construction
  • Beginning of construction
  • Foundations in place
  • First walls are taking shape
  • Office section developing fast

. The Factory . Construction phases 1 to 3 (2011 – 2015)

  • First construction phase - April 2011 / December 2011
  • First construction phase - April 2011 / December 2011
  • First construction phase - April 2011 / December 2011
  • First construction phase - April 2011 / December 2011
  • First construction phase - April 2011 / December 2011
  • First construction phase of the new plant. Transfer in January 2012.
  • Second construction phase - November 2011 / June 2012
  • Second construction phase - November 2011 / June 2012
  • Second construction phase - November 2011 / June 2012
  • Assembly area detail
  • Production area detail
  • Welding area detail
  • Third construction phase - September of 2014
  • Third construction phase - December of 2014
  • Third construction phase - January of 2015
  • Third construction phase - February of 2015
  • Third construction phase - Final